I'm no different to any who are totally Koi Kichy and not long after it's completion
my mind started wandering. We had an area to the right of the pond that if we planted out any plants of more then a few inches
would obscure our view of the pond from our lounge picture window. So after a little chat with Lynn it was decided that the
pond would be enlarged to encompass this area.
In the photo below it can be seen
where I had removed soil from the enlargement area and had started removing rock, while the pond was still up and running.
Photo taken summer 2001.
In October 2001 the pond was taken out of commission
and the real work started in earnest! A friend of mine has a mini digger and prices per day were worked out, he also
hired a mini dumper to remove the spoil to my back drive, where he would later collect the rock spoil for dumping.

Unfortunately once the digger had removed the area of rock that was in the area where
the pond was being enlarged the digger was not man enough to break the rock from the floor, so I had to break it out little
at a time with the Kango and then the machine would remove the rock to the dumper.

Click on the thumbnails below for a larger photo.

Over the coarse of two weekends we had managed to remove the rock to a depth of 5'. The
rock pile on my back drive had grown huge and the Saturday following Stuart the digger driver spent loading a 20 ton tripping
trailer pulled by a 4 wheel drive tractor. Stuart drove the tractor with load 4 miles to a farm on moorland, where the rock
was used for farm tracks. It took 8 full loads. Below is a photo taken after about half the spoil had been removed. The pile
was stacked 8' tall!
Only a small amount of work was carried out during summer of 2002 as the noise from the
Kango is quite loud and did not want to upset the neighbors to much.
This pond
was going to be 6' deep come hell or high water, so it was back on my own with the Kango to remove the last foot, plus
benching, plus pipe runs. I had been working evening and weekends for a couple of weeks when I decided that a roof was going
to be a must, as It would take me at least the whole of the winter to remove the rock down to the given depth. So the next
weekend was spent building the roof. On top of the timbers I nailed plastic mesh, over that I laid polythene and capped that
off with another layer of plastic mesh, with hope that this would make it strong enough to last the winter. This was built
in November 2002
It was not quite long enough to cover the full
length of the pond as the longest timbers I could buy were just over 6mtr, but once the polythene was on the gaps could be
filled.
